Surprise! --- Crunch Time

It's Wednesday, January 29. Everyone said that they were coming this week. Brian and Ray, from Ray's Plumbing came on Tuesday and ran almost all the water lines, set up the shower, and placed the mat in the bottom of the shower so we can pour concrete for the base. No one today so it'll be busy Thursday and Friday with electrical and heating to finish . Andy, our cabinet maker said that the cabinets are done. Next week Elite Builders return to tape all the joints and insulate the area where the walls and ceiling come together. I called the building inspector for the mechanical inspection. If everything is OK we'll be ready to hang the drywall and insulate the sill areas. In addition to everything else the siding is supposed to be here next Thursday. Picked up the last window for the lower bathroom today. 12:30 p.m. I'm heading North to check on the old house and see if the new renter has arrived.